Critical Path Analysis.

Consider the following Critical Path Analysis. You may assume statistical independence among all events (this makes the mathematical analysis easier.)

1. Activity sequences “A-D-J”, “B-F-K”, and “C-H-L” are critical paths, based on “expected” (50 percent) path estimates. What is probabaility that the project will be late? Show your work. (20 points)

2. Suppose project sponsors and stakeholders put political pressure on the project team and they modify their estimates to a more optimistic estimate and now estimates are likely to be 30% early and 70% likely to be late. Now, what is the is probabaility that the project will be late? Show your work. (20 points)

3. The project sponsor is still unsatisfied with the delivery date. He asks the project manager to reallocate the resources and eliminate any slack or float. The project manager successfully complies and eliminates all slacks or floats and shortens the project duration. (But, now every path is a critical path.) Now, how does that change the probability that the project will be late? (Hint: think carefully about this scenario. (The math becomes complicated and I do not expect you to calculate the probability of being late.) Explain and justify your answer to your project sponsor. (20 points)

4. In general, Is it a good idea to reallocate the resources and eliminate any slack or float? (20 points, hint be careful and think about this question carefully.)

5. What lessons do you take from these results? (20 points)

admin

Share
Published by
admin

Recent Posts

Childbirth

For this short paper activity, you will learn about the three delays model, which explains…

1 year ago

Literature

 This is a short essay that compares a common theme or motif in two works…

1 year ago

Hospital Adult Medical Surgical Collaboration Area

Topic : Hospital adult medical surgical collaboration area a. Current Menu Analysis (5 points/5%) Analyze…

1 year ago

Predictive and Qualitative Analysis Report

As a sales manager, you will use statistical methods to support actionable business decisions for Pastas R Us,…

1 year ago

Business Intelligence

Read the business intelligence articles: Getting to Know the World of Business Intelligence Business intelligence…

1 year ago

Alcohol Abuse

The behaviors of a population can put it at risk for specific health conditions. Studies…

1 year ago